Facturas compra de materiales (Corte de Cuentas).
Factura Filtro Tipo Y 2"
Factura 30 ladrillos.
Apto | Propietario | Monto |
PB-A | Adais Pariacano | 220bs |
PB-B | Yosmer Benitez | 220bs |
PB-C | Milyari Lopez | 220bs |
PB-D | Milagros Guerrero | 220bs |
PB-E | Larry Rivero | 110bs |
PB-F | Xiomara Rojas | 220bs |
1-A | Marleny Rivas | 220bs |
1-B | Dayana Altuve | 0 |
1-C | Jose Godoy | 220bs |
1-D | Miguel Delgado | 220bs |
1-E | Belkis Fuentes | 220bs |
1-F | Adriana Blanco | 220bs |
2-A | Luis Jose Suarez | 220bs |
2-B | Marco Antonio Cordero | 220bs |
2-C | Victor Luna | 220bs |
2-D | Yelitza Guevara | 220bs |
2-E | Noel Blanco | 220bs |
2-F | Joel Blanco | 220bs |
3-A | Maryorie Contreras | 220bs |
3-B | Carlos Gutierrez | 220bs |
3-C | Agustin Sifontes | 220bs |
3-D | Nancy Frias | 220bs |
3-E | Luz Marina Contreras | 220bs |
3-F | Jack Velasquez | 220bs |
4-A | Newman Mieres | 220bs |
4-B | Javier Rincon | 220bs |
4-C | Maria Medina | 220bs |
4-D | Ender Domador | 220bs |
4-E | Tatiana Lafaurie | 220bs |
4-F | Nicolas Guido | 220bs |
6270bs |
Mano de Obra | Monto | Resta | |
Plomeria | 3.000,00 | 0,00 | |
Albañil | 800,00 | 0,00 | |
Total | 3.800,00 | 0,00 | |
Materiales | |||
Ladrillos 30 | 206,98 | Comprado | |
Ladrillos 30 | 239,91 | Comprado | |
Filtro tipo Y dos pulgadas | 307,88 | Comprado | |
Llaves de Paso 2" | 800,00 | Pagado Sr. Butte | |
Líquidos Tuberias 1 Cuñete | 500,00 | Pagado Sr. Butte | |
Otros Materiales(Cemento,Polvillo Saco Escombro) | 88,00 | Comprado | |
Total Materiales | 2.142,77 | ||
Total General | 5.942,77 | ||
Total a Recaudar | 6.600,00 | ||
Diferencia Aproximada | 657,23 |
Total Gastos contra factura: 2.142,77bs
Total Pagado Mano de Obra 01/06/2011: 3.800,00bs
Total Recaudado : 6.270,00bs
Total General : 327,23bs